Clubhouse Renovations June 1 to July 8
Editor: Brian Lasby
Date: 2026-05-24
Clubhouse Renovation - June 1 to August 8
IMPORTANT ACTIVITIES
Work on the Roof begins June 1 - June 25
Men's Washroom June 18 - July 7 - will be closed these dates. Portapotty on site.
Parking Lot will be closed because of construction Dumpster. Access will be restricted to 4 foot wide path to front doors.
Access to Locker Room Restricted - June 18 - June 22
There will be disruption to some tag matches. Members will be advised of changes to play
Tournaments on July 1, 7 and August 3 will NOT be cancelled.
Work includes installation of new roof, renovation of Men's Washroom, replace HVAC, windows, update electrical and water systems
Members will receive weekly updates on the progress of the project. Watch your email.